Fire Headquarters Construction Update  

Delphi Contractors has recently contracted with GFM Enterprises of Truro to conduct all of the required site work for the Fire Headquarters construction project. GFM will be responsible for all site work including excavation, demolition, drainage and utility installation, silt fencing, foundation, curbing, and paving services.

Demolition of the former water department facility and the natural resources storage building started on Monday February 13 (see attached pictures). Silt fencing and runoff containment systems have also been installed. The demolition is scheduled to be complete by the week of February 20th after which the temporary construction entrance, tree pruning and removal, and new utility pole installation will take place.